Dept. of Trans. PROGRESS Serial No. Contract No. 22-173-07-28 02-1H1104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-LAS-299-25.6/25.6 NONE Progress payment No. 024 Payment period ending: 06-20-22 WALSH CONSTRUCTION COMPANY II LLC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,185,695.00 24,000.00 2. a. Extra Work 786,710.52 71,737.30 b. Adustment Comp. -15,401.64 0.00 3. Materials on Hand 4. Earned Subject to Retention 13,957,003.88 95,737.30 5. Mobilization 6. Total Work Completed 13,957,003.88 7. Deductions -15,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,942,003.88 95,737.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 95,737.30