Dept. of Trans. PROGRESS Serial No. Contract No. 25-021-10-43 02-1H3604 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 34% Location: Federal Project: 02-SIS-96-76.8/78.0 NONE Progress payment No. 007 Payment period ending: 01-20-25 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,731,394.85 1,532,678.22 2. a. Extra Work 38,445.00 0.00 b. Adustment Comp. 3. Materials on Hand 186,341.00 186,341.00 4. Earned Subject to Retention 14,956,180.85 1,719,019.22 5. Mobilization 2,945,000.00 0.00 6. Total Work Completed 17,714,839.85 7. Deductions -15,590.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,885,590.85 1,719,019.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,719,019.22