Dept. of Trans. PROGRESS Serial No. Contract No. 25-168-12-44 02-1H3604 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 53% Location: Federal Project: 02-SIS-96-76.8/78.0 NONE Progress payment No. 012 Payment period ending: 06-20-25 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,291,563.13 2,583,708.20 2. a. Extra Work 192,323.63 0.00 b. Adustment Comp. 3. Materials on Hand 531,234.45 0.00 4. Earned Subject to Retention 23,015,121.21 2,583,708.20 5. Mobilization 3,100,000.00 0.00 6. Total Work Completed 25,583,886.76 7. Deductions -11,590.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,103,531.21 2,583,708.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,583,708.20