Dept. of Trans. PROGRESS Serial No. Contract No. 19-232-13-34 02-1H4404 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 48% Location: Federal Project: 02-LAS-44-31.9/32.6 HSNH-P044(58) Progress payment No. 003 Payment period ending: 08-20-19 HAT CREEK CONSTRUCTION & MATERIALS INC 24339 STATE HWY 89 N BURNEY CA 96013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 771,931.88 511,699.48 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 771,931.88 511,699.48 5. Mobilization 213,708.20 44,991.20 6. Total Work Completed 985,640.08 7. Deductions -1,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 984,640.08 555,690.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 555,690.68