Dept. of Trans. PROGRESS Serial No. Contract No. 23-170-14-01 02-1H5204 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 23% Location: Federal Project: 02-SIS-3-46.8/48.0 ACNH-X093(10) 02-SIS-263-49.1/49.4 Progress payment No. 010 Payment period ending: 06-20-23 MYERS SHEA A JOINT VENTURE 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,966,507.10 3,312,679.99 2. a. Extra Work 211,478.49 0.00 b. Adustment Comp. 3. Materials on Hand 569,337.37 -147,704.88 4. Earned Subject to Retention 16,747,322.96 3,164,975.11 5. Mobilization 6,052,450.00 0.00 6. Total Work Completed 22,230,435.59 7. Deductions -24,346.07 -18,912.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,775,426.89 3,146,063.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,146,063.11