Dept. of Trans. PROGRESS Serial No. Contract No. 24-263-09-29 02-1H5204 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 85% Location: Federal Project: 02-SIS-3-46.8/48.0 ACNH-X093(10) 02-SIS-263-49.1/49.4 Progress payment No. 025 Payment period ending: 09-20-24 MYERS SHEA A JOINT VENTURE 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 50,211,575.14 812,247.88 2. a. Extra Work 626,695.51 0.00 b. Adustment Comp. -82,136.23 0.00 3. Materials on Hand 4. Earned Subject to Retention 50,756,134.42 812,247.88 5. Mobilization 6,371,000.00 0.00 6. Total Work Completed 57,127,134.42 7. Deductions -21,509.55 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 57,105,624.87 822,247.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 822,247.88