Dept. of Trans. PROGRESS Serial No. Contract No. 24-295-14-18 02-1H58U4 PROGRESS PAYMENT VOUCHER %complete: %time: 15% 23% Location: Federal Project: 02-PLU-70-58.2/R78.4 ACNH-P070(146) Progress payment No. 010 Payment period ending: 10-20-24 MERCER FRASER COMPANY PO BOX 1006 EUREKA CA 95502-1006 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,811,739.11 2,300,063.10 2. a. Extra Work b. Adustment Comp. -50,000.00 0.00 3. Materials on Hand 2,394,033.39 -321,052.35 4. Earned Subject to Retention 11,155,772.50 1,979,010.75 5. Mobilization 5,987,955.69 0.00 6. Total Work Completed 14,749,694.80 7. Deductions -32,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,111,728.19 1,977,010.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,977,010.75