Dept. of Trans. PROGRESS Serial No. Contract No. 25-233-13-13 02-1H58U4 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 35% Location: Federal Project: 02-PLU-70-58.2/R78.4 ACNH-P070(146) Progress payment No. 020 Payment period ending: 08-20-25 MERCER FRASER COMPANY PO BOX 1006 EUREKA CA 95502-1006 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,888,146.28 3,223,412.98 2. a. Extra Work 7,197,210.16 0.00 b. Adustment Comp. -35,000.00 0.00 3. Materials on Hand 2,885,271.00 -110,881.00 4. Earned Subject to Retention 33,935,627.44 3,112,531.98 5. Mobilization 7,584,743.87 0.00 6. Total Work Completed 38,635,100.31 7. Deductions -22,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 41,498,371.31 3,102,531.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,102,531.98