Dept. of Trans. PROGRESS Serial No. Contract No. 24-053-12-04 02-1H6804 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 57% Location: Federal Project: 02-TEH-5-40.5/41.9 NONE RCRO-SSIN-G(.) Progress payment No. 010 Payment period ending: 02-20-24 MCCUEN CONSTRUCTION INC 3269 SWETZER RD LOOMIS CA 95650 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,798,309.89 1,157,146.53 2. a. Extra Work 834,262.09 0.00 b. Adustment Comp. -5,449.28 0.00 3. Materials on Hand 70,977.00 -92,147.00 4. Earned Subject to Retention 13,698,099.70 1,064,999.53 5. Mobilization 6. Total Work Completed 13,627,122.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,698,099.70 1,064,999.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,064,999.53