Dept. of Trans. PROGRESS Serial No. Contract No. 24-206-15-24 02-1H6804 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 86% Location: Federal Project: 02-TEH-5-40.5/41.9 NONE RCRO-SSIN-G(.) Progress payment No. 015 Payment period ending: 07-20-24 MCCUEN CONSTRUCTION INC 3269 SWETZER RD LOOMIS CA 95650 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,367,030.97 725,170.18 2. a. Extra Work 1,157,035.25 109,196.10 b. Adustment Comp. 63,677.79 2,568.00 3. Materials on Hand 4. Earned Subject to Retention 20,587,744.01 836,934.28 5. Mobilization 6. Total Work Completed 20,587,744.01 7. Deductions -453,618.50 -453,618.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,134,125.51 383,315.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 383,315.78