Dept. of Trans. PROGRESS Serial No. Contract No. 23-298-10-50 02-1H7004 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 96% Location: Federal Project: 02-TRI-299-64.6/71.8 NONE Progress payment No. 003 Payment period ending: 10-20-23 R BROWN CONSTRUCTION CO INC PO BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 690,302.50 359,173.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 690,302.50 359,173.00 5. Mobilization 156,750.00 33,000.00 6. Total Work Completed 847,052.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 847,052.50 392,173.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 392,173.00