Dept. of Trans. PROGRESS Serial No. Contract No. 22-166-16-08 02-1H7904 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 36% Location: Federal Project: 02-PLU-70-36.8/R62.5 NONE Progress payment No. 002 Payment period ending: 06-20-22 STEWART ENGINEERING INC PO BOX 990010 REDDING CA 96099 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 468,766.00 228,964.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 468,766.00 228,964.00 5. Mobilization 162,450.00 34,200.00 6. Total Work Completed 631,216.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 631,216.00 263,164.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 263,164.00