Dept. of Trans. PROGRESS Serial No. Contract No. 18-236-09-53 02-1H9404 PROGRESS PAYMENT VOUCHER %complete: %time: 28% 16% Location: Federal Project: 02-SHA-999 NONE Progress payment No. 001 Payment period ending: 08-20-18 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 106,155.00 106,155.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 9,427.00 9,427.00 4. Earned Subject to Retention 115,582.00 115,582.00 5. Mobilization 29,766.35 29,766.35 6. Total Work Completed 135,921.35 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 145,348.35 145,348.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 145,348.35