Dept. of Trans. PROGRESS Serial No. Contract No. 18-235-12-15 02-1H9504 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 25% Location: Federal Project: 02-SIS-999 NONE Progress payment No. 002 Payment period ending: 08-20-18 AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC 2990 BAY VISTA CT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 330,126.90 260,452.60 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 330,126.90 260,452.60 5. Mobilization 83,600.00 39,600.00 6. Total Work Completed 413,726.90 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 413,726.90 300,052.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 300,052.60