Dept. of Trans. PROGRESS Serial No. Contract No. 15-355-09-26 02-1H9604 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 50% Location: Federal Project: 02-VAR NONE Progress payment No. 003 Payment period ending: 12-20-15 MEYERS EARTHWORK, INC. P.O. BOX 493730 REDDING, CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 132,211.10 107,022.07 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 132,211.10 107,022.07 5. Mobilization 6. Total Work Completed 132,211.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 132,211.10 107,022.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 107,022.07