Dept. of Trans. PROGRESS Serial No. Contract No. 26-202-10-11 02-1J2904 PROGRESS PAYMENT VOUCHER %complete: %time: 47% 35% Location: Federal Project: 02-SHA-299-88.1/89.5 PTST-S299(164) Progress payment No. 003 Payment period ending: 07-20-26 BUGLER CONSTRUCTION INC 4847 HOPYARD RD #4 #395 PLEASANTON CA 94588 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,522,701.00 1,391,584.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -873,037.56 4. Earned Subject to Retention 3,522,701.00 518,546.94 5. Mobilization 807,500.00 0.00 6. Total Work Completed 4,330,201.00 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,325,201.00 513,546.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 513,546.94