Dept. of Trans. PROGRESS Serial No. Contract No. 26-265-13-17 02-1J2904 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 69% Location: Federal Project: 02-SHA-299-88.1/89.5 PTST-S299(164) Progress payment No. 006 Payment period ending: 09-20-26 BUGLER CONSTRUCTION INC 4847 HOPYARD RD #4 #395 PLEASANTON CA 94588 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,416,788.00 2,158,506.00 2. a. Extra Work 244,228.67 235,159.32 b. Adustment Comp. -12,500.00 -12,500.00 3. Materials on Hand 64,610.00 -258,440.00 4. Earned Subject to Retention 7,713,126.67 2,122,725.32 5. Mobilization 850,000.00 0.00 6. Total Work Completed 8,498,516.67 7. Deductions -25,418.18 304,732.62 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,537,708.49 2,427,457.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,427,457.94