Dept. of Trans. PROGRESS Serial No. Contract No. 26-299-09-01 02-1J2904 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 97% Location: Federal Project: 02-SHA-299-88.1/89.5 PTST-S299(164) Progress payment No. 007 Payment period ending: 10-20-26 BUGLER CONSTRUCTION INC 4847 HOPYARD RD #4 #395 PLEASANTON CA 94588 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,201,852.00 785,064.00 2. a. Extra Work 401,284.14 157,055.47 b. Adustment Comp. -12,500.00 0.00 3. Materials on Hand 0.00 -64,610.00 4. Earned Subject to Retention 8,590,636.14 877,509.47 5. Mobilization 850,000.00 0.00 6. Total Work Completed 9,440,636.14 7. Deductions -25,418.18 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,415,217.96 877,509.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 877,509.47