Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 25-003-09-31 02-1J7004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-TRI-299-46.2 NONE Progress payment No. 004 Payment period ending: 12-05-24 STIMPEL-WIEBELHAUS ASSOCIATES INC PO BOX 492335 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 655,519.20 91,450.00 2. a. Extra Work 7,246.27 7,246.27 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 662,765.47 98,696.27 5. Mobilization 80,000.00 0.00 6. Total Work Completed 742,765.47 7. Deductions -34,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 708,765.47 78,696.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 78,696.27