Dept. of Trans. PROGRESS Serial No. Contract No. 25-260-08-57 02-1J75U4 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 43% Location: Federal Project: 02-LAS-36-14.4/R16.8 HSNH-S036(121) Progress payment No. 005 Payment period ending: 09-20-25 HAT CREEK CONSTRUCTION & MATERIALS INC 24339 STATE HWY 89 N BURNEY CA 96013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,203,786.80 1,369,751.28 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 216,966.14 -24,832.50 4. Earned Subject to Retention 3,420,752.94 1,344,918.78 5. Mobilization 1,306,250.00 275,000.00 6. Total Work Completed 4,510,036.80 7. Deductions -391,777.28 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,335,225.66 1,619,918.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,619,918.78