Dept. of Trans. PROGRESS Serial No. Contract No. 24-239-08-45 02-1K8504 PROGRESS PAYMENT VOUCHER %complete: %time: 15% 30% Location: Federal Project: 02-LAS-36-123.0/12.3 NONE Progress payment No. 001 Payment period ending: 07-20-24 DIG IT CONSTRUCTION INC. PO BOX 494 CHESTER CA 96020 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 151,737.82 151,737.82 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 151,737.82 151,737.82 5. Mobilization 6. Total Work Completed 151,737.82 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 149,737.82 149,737.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 149,737.82