Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 24-338-14-03 02-1K8504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-LAS-36-123.0/12.3 NONE Progress payment No. 004 Payment period ending: 10-11-24 DIG IT CONSTRUCTION INC. PO BOX 494 CHESTER CA 96020 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,740.00 8,740.00 2. a. Extra Work 958,139.67 85,442.18 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 966,879.67 94,182.18 5. Mobilization 6. Total Work Completed 966,879.67 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 964,879.67 94,182.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 94,182.18