Dept. of Trans. PROGRESS Serial No. Contract No. 06-355-13-18 02-251474 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 64% 02-TEH-99-7.9/8.9 Federal Project: NONE Progress payment No. 08 Payment period ending: 12-20-06 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,602,287.45 479,819.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 77,447.20 -68,365.00 4. Earned Subject to Retention 2,679,734.65 411,454.00 5. Mobilization 501,500.00 25,075.00 6. Total Work Completed 3,103,787.45 7. Deductions 8. a.Contract Retentions -133,986.73 -20,572.70 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,047,247.92 415,956.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 415,956.30