Dept. of Trans. PROGRESS Serial No. Contract No. 07-025-12-58 02-251474 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 65% 02-TEH-99-7.9/8.9 Federal Project: NONE Progress payment No. 09 Payment period ending: 01-19-07 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,923,876.45 321,589.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -77,447.20 4. Earned Subject to Retention 2,923,876.45 244,141.80 5. Mobilization 501,500.00 0.00 6. Total Work Completed 3,425,376.45 7. Deductions 8. a.Contract Retentions -146,193.82 -12,207.09 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,279,182.63 231,934.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 231,934.71