Dept. of Trans. PROGRESS Serial No. Contract No. 07-081-10-45 02-251474 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 65% 02-TEH-99-7.9/8.9 Federal Project: NONE Progress payment No. 11 Payment period ending: 03-20-07 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 96049 Escrow No. 02249 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,149,775.45 224,360.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -53,097.00 4. Earned Subject to Retention 3,149,775.45 171,263.50 5. Mobilization 501,500.00 0.00 6. Total Work Completed 3,651,275.45 7. Deductions 8. a.Contract Retentions -157,488.77 -8,563.17 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,493,786.68 162,700.33 10. Reduction Amt to Escrow 11. Payment to Escrow 157,480.00 12. Net Pymt. this Estimate 162,700.33