Dept. of Trans. PROGRESS Serial No. Contract No. 07-234-15-13 02-251474 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 82% 02-TEH-99-7.9/8.9 Federal Project: NONE Progress payment No. 15 Payment period ending: 08-20-07 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 96049 Escrow No. 02249 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,376,549.87 45,300.00 2.a. Extra Work 62,493.05 35,361.15 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 4,439,042.92 80,661.15 5. Mobilization 501,500.00 0.00 6. Total Work Completed 4,940,542.92 7. Deductions 8. a.Contract Retentions -221,952.15 -4,033.06 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,718,590.77 76,628.09 10. Reduction Amt to Escrow 11. Payment to Escrow 221,950.00 12. Net Pymt. this Estimate 76,628.09