Dept. of Trans. PROGRESS Serial No. Contract No. 03-141-13-50 02-258504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 1% 4% 02-LAS-395-11.8/24.8 Federal Project: ACNH-P395(197) Progress payment No. 01 Payment period ending: 05-20-03 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 95827 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 115,322.30 115,322.30 2.a. Extra Work b. Adjustment Comp. -4,250.00 -4,250.00 3. Materials on Hand 4. Earned Subject to Retention 111,072.30 111,072.30 5. Mobilization 6. Total Work Completed 111,072.30 7. Deductions 8. a.Contract Retentions -11,107.23 -11,107.23 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 99,965.07 99,965.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 99,965.07