Dept. of Trans. PROGRESS Serial No. Contract No. 03-202-15-01 02-258504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 19% 02-LAS-395-11.8/24.8 Federal Project: ACNH-P395(197) Progress payment No. 03 Payment period ending: 07-18-03 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 95827 Escrow No. 02091 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,119,059.07 589,449.50 2.a. Extra Work 13,864.39 13,864.39 b. Adjustment Comp. -4,250.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,128,673.46 603,313.89 5. Mobilization 456,000.00 152,000.00 6. Total Work Completed 1,584,673.46 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -112,867.35 -60,331.39 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,461,806.11 684,982.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 684,982.50