Dept. of Trans. PROGRESS Serial No. Contract No. 03-237-15-58 02-258504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 24% 02-LAS-395-11.8/24.8 Federal Project: ACNH-P395(197) Progress payment No. 04 Payment period ending: 08-20-03 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 95827 Escrow No. 02091 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,557,556.72 438,497.65 2.a. Extra Work 18,669.27 4,804.88 b. Adjustment Comp. -1,886.22 2,363.78 3. Materials on Hand 4. Earned Subject to Retention 1,574,339.77 445,666.31 5. Mobilization 456,000.00 0.00 6. Total Work Completed 2,030,339.77 7. Deductions -80,000.00 -70,000.00 8. a.Contract Retentions -157,433.98 -44,566.63 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,792,905.79 331,099.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 331,099.68