Dept. of Trans. PROGRESS Serial No. Contract No. 03-267-07-30 02-258504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 31% 32% 02-LAS-395-11.8/24.8 Federal Project: ACNH-P395(197) Progress payment No. 05 Payment period ending: 09-19-03 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 95827 Escrow No. 02091 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,233,604.57 676,047.85 2.a. Extra Work 18,669.27 0.00 b. Adjustment Comp. -1,886.22 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,250,387.62 676,047.85 5. Mobilization 577,600.00 121,600.00 6. Total Work Completed 2,827,987.62 7. Deductions -10,000.00 70,000.00 8. a.Contract Retentions -169,433.38 -11,999.40 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,648,554.24 855,648.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 855,648.45