Dept. of Trans. PROGRESS Serial No. Contract No. 03-296-13-39 02-258504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 39% 02-LAS-395-11.8/24.8 Federal Project: ACNH-P395(197) Progress payment No. 06 Payment period ending: 10-20-03 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 95827 Escrow No. 02091 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,354,243.67 1,120,639.10 2.a. Extra Work 42,414.95 23,745.68 b. Adjustment Comp. -1,886.22 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,394,772.40 1,144,384.78 5. Mobilization 577,600.00 0.00 6. Total Work Completed 3,972,372.40 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -169,738.62 -305.24 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,792,633.78 1,144,079.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,144,079.54