Dept. of Trans. PROGRESS Serial No. Contract No. 03-329-08-25 02-258504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 47% 02-LAS-395-11.8/24.8 Federal Project: ACNH-P395(197) Progress payment No. 07 Payment period ending: 11-20-03 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 95827 Escrow No. 02091 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,241,032.57 886,788.90 2.a. Extra Work 42,414.95 0.00 b. Adjustment Comp. -1,886.22 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,281,561.30 886,788.90 5. Mobilization 577,600.00 0.00 6. Total Work Completed 4,859,161.30 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -214,078.07 -44,339.45 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,635,083.23 842,449.45 10. Reduction Amt to Escrow 11. Payment to Escrow 200,000.00 12. Net Pymt. this Estimate 842,449.45