Dept. of Trans. PROGRESS Serial No. Contract No. 03-356-14-20 02-258504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 54% 02-LAS-395-11.8/24.8 Federal Project: ACNH-P395(197) Progress payment No. 08 Payment period ending: 12-19-03 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 95827 Escrow No. 02091 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,442,577.19 201,544.62 2.a. Extra Work 84,043.81 41,628.86 b. Adjustment Comp. -1,886.22 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,524,734.78 243,173.48 5. Mobilization 608,000.00 30,400.00 6. Total Work Completed 5,132,734.78 7. Deductions -60,000.00 -50,000.00 8. a.Contract Retentions -226,236.74 -12,158.67 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,846,498.04 211,414.81 10. Reduction Amt to Escrow 11. Payment to Escrow 200,000.00 12. Net Pymt. this Estimate 211,414.81