Dept. of Trans. PROGRESS Serial No. Contract No. 04-299-11-13 02-258504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 100% 02-LAS-395-11.8/24.8 Federal Project: ACNH-P395(197) Progress payment No. 17 Payment period ending: 10-20-04 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 95827 Escrow No. 02091 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,853,342.62 11,415.00 2.a. Extra Work 1,333,120.98 64,999.39 b. Adjustment Comp. 10,657.70 -5,283.92 3. Materials on Hand 4. Earned Subject to Retention 9,197,121.30 71,130.47 5. Mobilization 608,000.00 0.00 6. Total Work Completed 9,805,121.30 7. Deductions -69,200.00 0.00 8. a.Contract Retentions -459,856.07 -3,556.53 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,276,065.23 67,573.94 10. Reduction Amt to Escrow 11. Payment to Escrow 450,000.00 12. Net Pymt. this Estimate 67,573.94