Dept. of Trans. PROGRESS Serial No. Contract No. 02-113-16-01 02-260124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 34% 02-SHA-5-R6.4/R7.6 Federal Project: ACNH-005-8(315) I-005-8(315) ACNH-005-8(N) Progress payment No. 14 Payment period ending: 04-19-02 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 01706 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,170,972.05 420,465.62 2.a. Extra Work 45,708.20 0.00 b. Adjustment Comp. -3,350.00 -3,350.00 3. Materials on Hand 441,953.27 -46,982.17 4. Earned Subject to Retention 5,655,283.52 370,133.45 5. Mobilization 1,520,000.00 0.00 6. Total Work Completed 6,733,330.25 7. Deductions 8. a.Contract Retentions -292,450.15 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,882,833.37 370,133.45 10. Reduction Amt to Escrow 11. Payment to Escrow 292,450.00 12. Net Pymt. this Estimate 370,133.45