Dept. of Trans. PROGRESS Serial No. Contract No. 02-144-11-41 02-260124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 34% 02-SHA-5-R6.4/R7.6 Federal Project: ACNH-005-8(315) I-005-8(315) ACNH-005-8(N) Progress payment No. 15 Payment period ending: 05-20-02 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 01706 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,683,610.76 512,638.71 2.a. Extra Work 45,708.20 0.00 b. Adjustment Comp. -3,350.00 0.00 3. Materials on Hand 384,041.81 -57,911.46 4. Earned Subject to Retention 6,110,010.77 454,727.25 5. Mobilization 1,520,000.00 0.00 6. Total Work Completed 7,245,968.96 7. Deductions 8. a.Contract Retentions -305,500.54 -13,050.39 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,324,510.23 441,676.86 10. Reduction Amt to Escrow 11. Payment to Escrow 305,500.00 12. Net Pymt. this Estimate 441,676.86