Dept. of Trans. PROGRESS Serial No. Contract No. 02-170-09-39 02-260124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 36% 02-SHA-5-R6.4/R7.6 Federal Project: ACNH-005-8(315) I-005-8(315) ACNH-005-8(N) Progress payment No. 16 Payment period ending: 06-20-02 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 01706 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,086,860.70 403,249.94 2.a. Extra Work 45,708.20 0.00 b. Adjustment Comp. -3,350.00 0.00 3. Materials on Hand 333,057.34 -50,984.47 4. Earned Subject to Retention 6,462,276.24 352,265.47 5. Mobilization 1,520,000.00 0.00 6. Total Work Completed 7,649,218.90 7. Deductions 8. a.Contract Retentions -323,113.81 -17,613.27 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,659,162.43 334,652.20 10. Reduction Amt to Escrow 11. Payment to Escrow 323,110.00 12. Net Pymt. this Estimate 334,652.20