Dept. of Trans. PROGRESS Serial No. Contract No. 02-203-16-36 02-260124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 39% 02-SHA-5-R6.4/R7.6 Federal Project: ACNH-005-8(315) I-005-8(315) ACNH-005-8(N) Progress payment No. 17 Payment period ending: 07-19-02 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 01706 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,621,955.68 535,094.98 2.a. Extra Work 45,708.20 0.00 b. Adjustment Comp. -3,350.00 0.00 3. Materials on Hand 222,146.69 -110,910.65 4. Earned Subject to Retention 6,886,460.57 424,184.33 5. Mobilization 1,520,000.00 0.00 6. Total Work Completed 8,184,313.88 7. Deductions 8. a.Contract Retentions -344,323.03 -21,209.22 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,062,137.54 402,975.11 10. Reduction Amt to Escrow 11. Payment to Escrow 344,320.00 12. Net Pymt. this Estimate 402,975.11