Dept. of Trans. PROGRESS Serial No. Contract No. 03-142-09-05 02-260124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 59% 02-SHA-5-R6.4/R7.6 Federal Project: ACNH-005-8(315) I-005-8(315) ACNH-005-8(N) Progress payment No. 27 Payment period ending: 05-20-03 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 01706 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,434,292.37 443,407.10 2.a. Extra Work 218,690.09 1,936.98 b. Adjustment Comp. 3,970.37 -1,650.00 3. Materials on Hand 264,925.11 0.00 4. Earned Subject to Retention 9,921,877.94 443,694.08 5. Mobilization 1,600,000.00 0.00 6. Total Work Completed 11,256,952.83 7. Deductions 8. a.Contract Retentions -496,093.90 -22,184.71 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,025,784.04 421,509.37 10. Reduction Amt to Escrow 11. Payment to Escrow 496,090.00 12. Net Pymt. this Estimate 421,509.37