Dept. of Trans. PROGRESS Serial No. Contract No. 04-146-12-40 02-260124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 86% 02-SHA-5-R6.4/R7.6 Federal Project: ACNH-005-8(315) I-005-8(315) ACNH-005-8(N) Progress payment No. 39 Payment period ending: 05-20-04 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 01706 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,286,230.09 119,080.61 2.a. Extra Work 415,931.83 0.00 b. Adjustment Comp. 9,947.43 0.00 3. Materials on Hand 0.00 -3,616.69 4. Earned Subject to Retention 13,712,109.35 115,463.92 5. Mobilization 1,600,000.00 0.00 6. Total Work Completed 15,312,109.35 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions -685,605.47 -5,773.20 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,625,503.88 108,690.72 10. Reduction Amt to Escrow 11. Payment to Escrow 685,600.00 12. Net Pymt. this Estimate 108,690.72