Dept. of Trans. SEMI-FINAL Serial No. Contract No. 06-339-11-51 02-288534 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-TRI-299-55.7/57.7 Federal Project: ACNH-P299(150) Progress payment No. 11 Payment period ending: 11-01-06 STEVE MANNING CONSTRUCTION INC P O BOX 491660 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,399,008.55 0.00 2.a. Extra Work 414,171.96 47,175.36 b. Adjustment Comp. -21,511.57 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,791,668.94 47,175.36 5. Mobilization 308,877.00 0.00 6. Total Work Completed 4,100,545.94 7. Deductions -34,000.00 20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,066,545.94 67,175.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 67,175.36