Dept. of Trans. PROGRESS Serial No. Contract No. 15-237-15-23 02-299714 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 43% Location: Federal Project: 02-MOD-299-39.3/40.4 STP-P299(188) Progress payment No. 002 Payment period ending: 08-20-15 ROCKY MOUNTAIN CONSTRUCTION 4815 TINGLEY LANE #A KLAMATH FALLS OR 97602 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 374,208.58 309,346.78 2. a. Extra Work 16,055.40 16,055.40 b. Adustment Comp. 3. Materials on Hand 15,200.00 -53,938.75 4. Earned Subject to Retention 405,463.98 271,463.43 5. Mobilization 128,442.26 42,814.09 6. Total Work Completed 518,706.24 7. Deductions -3,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 530,906.24 311,277.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 311,277.52