Dept. of Trans. PROGRESS Serial No. Contract No. 15-265-10-54 02-299714 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 65% Location: Federal Project: 02-MOD-299-39.3/40.4 STP-P299(188) Progress payment No. 003 Payment period ending: 09-20-15 ROCKY MOUNTAIN CONSTRUCTION 4815 TINGLEY LANE #A KLAMATH FALLS OR 97602 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 635,986.65 261,778.08 2. a. Extra Work 23,996.38 7,940.98 b. Adustment Comp. 3. Materials on Hand 0.00 -15,200.00 4. Earned Subject to Retention 659,983.03 254,519.06 5. Mobilization 162,693.53 34,251.27 6. Total Work Completed 822,676.56 7. Deductions -4,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 818,676.56 287,770.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 287,770.33