Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-022-09-15 02-299714 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-MOD-299-39.3/40.4 STP-P299(188) Progress payment No. 007 Payment period ending: 12-08-15 ROCKY MOUNTAIN CONSTRUCTION 4815 TINGLEY LANE #A KLAMATH FALLS OR 97602 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,733,228.13 0.00 2. a. Extra Work 90,112.70 12,579.76 b. Adustment Comp. 150,306.00 150,306.00 3. Materials on Hand 4. Earned Subject to Retention 1,973,646.83 162,885.76 5. Mobilization 171,256.35 0.00 6. Total Work Completed 2,144,903.18 7. Deductions -27,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,117,903.18 172,885.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 172,885.76