Dept. of Trans. PROGRESS Serial No. Contract No. 18-115-07-47 02-2C0904 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 42% Location: Federal Project: 02-PLU-70-50.6/51.7 ACST-P070-1(05E) Progress payment No. 011 Payment period ending: 04-20-18 MCM CONSTRUCTION INC 6413 32ND ST NO HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,128,191.43 112,327.00 2. a. Extra Work 462,474.16 299,431.55 b. Adustment Comp. 124,393.85 94,535.78 3. Materials on Hand 46,905.52 0.00 4. Earned Subject to Retention 3,761,964.96 506,294.33 5. Mobilization 964,218.54 0.00 6. Total Work Completed 4,679,277.98 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,726,183.50 506,294.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 506,294.33