Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 12-059-08-59 02-2C1104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-TEH-99-13.9/14.2 Federal Project: ACNH-P099(528) Progress payment No. 09 Payment period ending: 12-20-11 BLAISDELL CONSTRUCTION INC P O BOX 938 ANDERSON CA 96007 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,300,028.46 540.00 2.a. Extra Work 190,278.19 19,083.51 b. Adjustment Comp. -8,254.95 -25,000.76 3. Materials on Hand 4. Earned Subject to Retention 1,482,051.70 -5,377.25 5. Mobilization 145,000.00 0.00 6. Total Work Completed 1,627,051.70 7. Deductions -45,044.40 -39,044.40 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,582,007.30 -44,421.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -44,421.65