Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-141-12-57 02-2C1304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-LAS-395-0.1/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 05-09-08 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,039,668.50 30,360.00 2.a. Extra Work 38,837.53 0.00 b. Adjustment Comp. -5,484.11 -6,701.35 3. Materials on Hand 4. Earned Subject to Retention 1,073,021.92 23,658.65 5. Mobilization 100,000.00 0.00 6. Total Work Completed 1,173,021.92 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -52,468.16 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 52,468.16 52,468.16 9. Total pay to Contractor 1,163,021.92 66,126.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 66,126.81