Dept. of Trans. PROGRESS Serial No. Contract No. 12-235-08-27 02-2C2214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 54% 02-MOD-299-3.2/3.5 Federal Project: BHST-PP29(916) Progress payment No. 05 Payment period ending: 08-20-12 Q & D CONSTRUCTION INC P O BOX 10865 RENO NV 89510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 804,336.16 279,507.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -28,410.95 4. Earned Subject to Retention 804,336.16 251,096.95 5. Mobilization 145,000.00 7,250.00 6. Total Work Completed 949,336.16 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 949,336.16 258,346.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 258,346.95