Dept. of Trans. PROGRESS Serial No. Contract No. 13-263-11-32 02-2C2254 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 43% 02-TEH-36-91.5/ .0 Federal Project: BHST-P036(95) Progress payment No. 03 Payment period ending: 09-17-13 STEELHEAD CONSTRUCTORS INC P O BOX 997 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 440,353.86 204,911.18 2.a. Extra Work 7,462.73 5,169.35 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 447,816.59 210,080.53 5. Mobilization 69,000.00 3,450.00 6. Total Work Completed 516,816.59 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 506,816.59 213,530.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 213,530.53