Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 13-196-10-40 02-2C2304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-SHA-5-30.6/ .0 Federal Project: ACBH-IM00(583) Progress payment No. 10 Payment period ending: 06-06-13 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,469,341.46 -55,500.00 2.a. Extra Work 77,753.36 51,701.46 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,547,094.82 -3,798.54 5. Mobilization 160,000.00 0.00 6. Total Work Completed 1,707,094.82 7. Deductions -20,000.00 -4,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,687,094.82 -7,798.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -7,798.54